Road Construction, Detours & Paving

Posted on: August 18, 2023

Main Street Paving Information

Main Street Flyer Final_Page_1

Construction Starts Tuesday, September 5th 

Resurfacing Limits – Pearson Avenue to West/East Hollis Street

Proposed Activity and Schedule –

Barrier Removal – 9/5

Casting Prep/Crosswalk Prep/Utility Prep – 9/5 to 9/8

Pavement Milling – 9/11 to 9/15

Base Paving – 9/16 (Saturday)

Casting/Utility Adjustment – 9/18 to 9/22

Finish Paving – 9/23 (Saturday)

Pavement Markings – 9/25 to 9/29

*schedule subject to change due to weather – updates will be posted to City website*

Work Hours –      5:00AM to 4:00PM

Traffic 

A minimum of one lane of traffic will be open in each direction during construction. While there will be construction throughout the month of September, major delays can be anticipated during the following activities – Pavement Milling | Base Paving | Finish Paving. To the best of our ability, all disruptions will be kept to a minimum. Variable message boards will be posted around the work zone to alert the public.

Parking – Parking will be restricted during major work activities – Pavement Milling | Base Paving | Finish Paving.