Below you will find the anticipated paving schedule for October 17th thru October 26th:
10/17/19 East Hollis Structure Work (Temple St. to Crown St.)
Taylor St. Milling Transitions & Structure Work
Conant Rd. Milling Transitions & Structure Work
Cheshire St. Milling Transitions
10/18/19 East Hollis Structure Work (Temple St. to Crown St.)
Taylor St. Structure Work
10/21/19 Allds St. Reclaiming
Pine Hill Rd. Structure Work
Mulberry St. Structure Work
10/22/19 Allds St. Reclaiming
Pine Hill Rd. Structure Work and Lane Widening at Charron Ave. Intersection
Gilman St. Structure Work
Cheshire St. Structure Work
10/23/19 Allds St. Reclaiming and Structure Work
10/24/19 Allds St. Reclaiming and Structure Work
10/25/19 Allds St. Reclaiming and Structure Work
Dublin Ave. Milling at Pine Hill Intersection
10/26/19 Taylor St. Paving
The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues.