Road Construction, Detours & Paving

Posted on: October 4, 2019

[ARCHIVED] Weekly Paving Update 10/5-10/11

Below you will find the anticipated paving schedule for October 5th thru October 11th:



10/5/19    
Ridge Rd. Structure Work
Conant Rd. Structure Work
10/7/19    
Allds St. Structure Work
Pine Hill Rd. Milling
Ridge Rd. Reclaiming & Milling 
Conant Rd. Reclaiming & Milling 
10/8/19    
Allds St. Structure Work
Pine Hill Rd. Milling
Conant Rd. Reclaiming & Milling 
10/9/19
East Hollis St. Milling
Taylor St. Reclaiming 
Cheshire St. Reclaiming 
Beard St. Milling Transitions 
Green St. Milling Transitions
Jackson St. Milling Transitions
Lemon St. Milling Transitions
Monroe St. Milling Transitions
Mulberry St. Milling Transitions
Terrace St. Milling Transitions
Warren St. Milling Transitions
10/10/19
Allds St. Milling
Taylor St. Reclaiming 
Cheshire St. Reclaiming
Beard St. Milling Transitions 
Green St. Milling Transitions
Jackson St. Milling Transitions
Lemon St. Milling Transitions
Monroe St. Milling Transitions
Mulberry St. Milling Transitions
Terrace St. Milling Transitions
Warren St. Milling Transitions
Conant Rd. Paving 
Ridge Rd. Paving 
Gillis St. Structure Work
10/11/19
Taylor St. Reclaiming & Structure Work
Cheshire St. Reclaiming & Structure Work
Beard St. Milling Transitions
Green St. Milling Transitions
Jackson St. Milling Transitions
Lemon St. Milling Transitions
Monroe St. Milling Transitions
Mulberry St. Milling Transitions
Terrace St. Milling Transitions
Warren St. Milling Transitions
Conant Rd. Structure Work
Ridge Rd. Structure Work
Gillis St. Structure Work 

The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issue