Below you will find the anticipated paving schedule for September 16th thru September 25th:
9/16 - Day - Gilson Road paving
9/17 - Day - Taylor Street, Mulberry Street, Gilman Street paving
9/18 - Day - Gillis Street structure work
9/19 - Day - Park Avenue structure work
9/19 - Night - West Hollis Street paving
9/20 - Day - Gilson Road, Taylor Street, Gilman Street and Mulberry Street structure work
9/20 - Night - West Hollis Street paving
9/23 - Night - West Hollis Street paving
9/24 - Night - Canal Street paving
9/25 - Night - Canal Street paving
The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues