Below you will find the anticipated paving schedule for September 6th thru September 15th:
9/6 - Structures adjustment on Woodfield Street, Gilson Street
9/9 - Paving in Church Street Neighborhood, Woodfield cul de sac
9/9 - Milling Gilson Street
9/9 - Structure Adjustments Green Street, Terrance Street, Monroe Street and Beard Street
9/10 - Paving Gilson Street
9/10 - Grading Gilson Street
9/10 - Milling Cheshire Street
9/11 - Paving Gilson Street
9/11 - Milling Gilman Street
9/12 - Paving Gilson Street
9/12 - Milling Gilman Street
9/12 - Milling Mulberry Street and Taylor Street
9/13- Grading Mulberry Street and Taylor Street
The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues.