Below you will find the anticipated paving schedule for August 19th thru August 29th:
Monday 8/19 - Day - Kinsley Street Paving (Exit 5 Exchange to Hanover Street)
Tuesday 8/20 - Day - Kinsley Street Paving (Exit 5 Exchange to Hanover Street)
Wednesday 8/21 - Day - Kinsley Street Paving (Exit 5 Exchange to Hanover Street)
Thursday 8/22 - Day - Kinsley Street structure work
Saturday 8/24 - Day - Kinsley Street Paving (Hanover Street to Main Street)
Sunday 8/25 - Night - West Hollis Street Paving
Monday 8/26 - Day - Kinsley Street Paving (Hanover Street to Main Street)
Monday 8/26 - Night - West Hollis Street Paving
Tuesday 8/27 - Night - West Hollis Street Paving
Wednesday 8/28 - Night - Canal Street Paving
Thursday 8/29 - Night - Can Street Paving
The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues.