Below you will find the anticipated paving schedule for August 4th thru August 9th:
Sunday 8/4 -Night - Kinsley Street Milling (St. Joseph Hospital to Hanover Street)
Sunday 8/4 - Night Canal Street Paving
Monday 8/5 - Night - West Hollis Street Milling
Monday 8/5 - Night - Canal Street Paving
Tuesday 8/6 - Day - Bedford Street Paving
Tuesday 8/6 - Day - Bedford Street Paving
Tuesday 8/6 - Night - Canal Street Paving (tentative)
Tuesday 8/6- Night - West Hollis Street Milling
Wednesday 8/7 - Day - Tenby Drive Paving
Wednesday 8/7 - Day - Almont Street Paving
Wednesday 8/7 - Day - Stevens Street Paving
Wednesday 8/7 - Night - West Hollis Street Milling
Thursday 8/8 - Day - Kinsley Street Paving (Hanover to Main)
Friday 8/9 - Day - Kinsley Street Paving (Hanover to Main)
The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues.