Below you will find the anticipated paving schedule for July 27th thru August 4th:
Saturday 7/27 - Day - Sidewalk work on Kinsley (Hanover to Main)
Sunday 7/28 - Night - Milling on Canal
Paving on Broad Street (Mall to Dublin Ave)
Monday 7/29 - Day - Loops and Structures on Canal
Sidewalk work on Kinsley (Hanover to Main)
Monday 7/29 - Night - Milling on Canal
Paving on Broad (Dublin to Coburn)
Tuesday 7/30 - Day - Loops and Structures on Canal
Sidewalk work on Kinsley (Hanover to Main)
Milling on Kinsley (Hanover to Main)
Tuesday 7/30 - Night - Milling Main Dunstable (West Hollis to Route 3 Southbound ramp)
Milling Kinsley (Main Dunstable to Hanover)
Wednesday 7/31 - Day - Loops and Structures on Canal
Sidewalk work on Kinsley (Hanover to Main)
Milling on Kinsley (Hanover to Main)
Wednesday 7/31 - Night - Milling Kinsley (Main Dunstable to Hanover)
Paving on Kinsley (Hanover to Main)
Thursday- 8/1 - Night - Milling on Kinsley (Hanover to Main)
Sunday - 8/4 - Night - Milling on West Hollis (Location TBD)
Paving on Canal (Location TBD)
The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues.