Road Construction, Detours & Paving

Posted on: July 12, 2019

[ARCHIVED] Paving Schedule for Week of July 15th thru July 19th

Below you will find the anticipated paving schedule for the week of July 15th through July 19th:

7/15 - Day: Broad Street Structure Work
7/15 - Day: Park Street Structure Work
7/15 - Night: Broad Street Traffic Loops (Exit 6 to Dublin Ave)
7/15 - Night: Somerset Pkwy and Amherst Street (Heading East towards Exit 7) - Permanent Markings/lines
7/16 - Day: Canal Street Structure Work
7/16 - Day: Amherst Street Permanent Markings (Somerset Pkwy to Merrimack Line)
7/16 - Day: Broad Street Structure Work (Exit 6 to Dublin)
7/16 - Day: Ducas Ave Paving
7/16 - Day: Beaver Street Paving
7/16 - Night: Broad Street Traffic Loops (Exit 6 to Dublin)
7/16 - Night: Somerset Pkwy and Amherst Street Permanent Markings (eastbound towards Exit 7)
7/17 - Day: Canal Street Structure Work
7/17 - Day: Kinsley Street Structure Work
7/17 - Day: Amherst Street Permanent Markings (Somerset Pkwy to Merrimack Line)
7/17 - Night: Broad Street Traffic Loops (Exit 6 to Dublin Ave)
7/18 - Day: Kinsley Street Structure Work
7/18 - Day: Bedford Street Paving
7/18 - Day: Parker Drive Paving
7/18 - Day: Almont Street Paving
7/18 - Night: Broad Street Paving (Coburn Ave heading east towards Exit 6)
7/19 - Day: Kinsley Street Structure Work

The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues