Below you will find the anticipated paving schedule for the week of June 22nd through June 28th. As always, this schedule is tentative and may change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues. “No Parking” signs will be posted in advance on these streets.
• Somerset Parkway (Night Time Paving on June 24, 2019)
• Gillis Street (Paving on June 24, 2019 )
• Coburn Ave (Paving on June 24, 2019 and June 25, 2019)
• Tenby Drive (Paving on June 25, 2019)
• Twilight Drive (Paving on June 26, 2019)
• Fowell Ave (Paving on June 26, 2019)
• Kinsley Street (Night Time Paving Work: Milling on June 26, 2019)
• Amherst Street (Night Time Paving: June 23, 2019 through June 28, 2019)
• Amherst Street (Daytime Paving-related work: June 24, 2019 through June 27, 2019)
• Broad Street (Night Time Paving: June 23rd)