Below you will find the anticipated paving schedule for the week of June 17th through June 21st.
(Night Time Paving; June 16, 2019 to June 21, 2019; 8 PM to 5AM)
(Day Time Work – Structure Adjustment and Traffic loop Installation; 7AM to 5PM)
(Possible Night Time Milling and Paving; June 17, 2019 through June 21, 2019; 7PM to 5AM).
· Cambridge Road * (Paving on June 18, 2019)
· Fairmount Street * (Paving on June 18, 2019)
Note: * These streets will be receiving shim/binder and/or final top course next week. Therefore, please be cautious as the pavement is hot and need some time to cool off.
The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues.