Road Construction, Detours & Paving

Posted on: June 7, 2019

[ARCHIVED] Paving Update for Week of June 10th thru June 14th

Below you will find the anticipated paving schedule for the week of June 10th through June 14th.  

Amherst Street (Night Time Milling; June 7, 2019; 8PM to 5AM)
 ·         Main Dunstable Road (Conant Road to Northeastern Boulevard)* (Paving on June 8, 2019; 7 AM to 5 PM)
 ·         Amherst Street (Night Time Milling; June 9, 2019 through June 12, 2019; 8 PM to 5 AM)
 ·         Amherst Street (Day Time Work – Structure Adjustment and Traffic Loop Installation; June 10, 2019 through June 14, 2019; 7 AM to 5 PM)
 ·         Amherst Street* (Night Time Paving; June 13, 2019 and June 14, 2019; 8 PM to 5AM)
 ·         Spit Brook Road* (Paving on June 10, 2019 through June 12, 2019; 7AM to 5 PM)
 ·         West Hollis Street (Night Time Milling – June 13, 2019; 8PM to 5AM)
 ·         Broad Street (Possible Night Time Milling and Paving; June 10, 2019 through June 14, 2019).
 ·         Stevens Street, Park Avenue, Fowell Avenue (drop and plate structures on June 10, 2019)
 ·         Pratt Street, Zellwood Street, and Lincoln Avenue (drop and plate structures on June 11, 2019)
 ·         Taylor Street and Gilman Street (drop and plate structures on June 12, 2019)
 ·         Twilight Drive and Tenby Drive  (drop and plate structures on June 13, 2019)
 ·         Cambridge Road* (Paving on June 13, 2019)
 ·         Tenby Drive and Gillis Street (drop and plate structures on June 14, 2019)
 ·         Cambridge Road (Berm installation on June 14, 2019)

Note: * These streets will be receiving shim/binder and/or final top course next week. Therefore, please be cautious as the pavement is hot and need some time to cool off.

The schedule is tentative and might change due to unforeseen circumstances such as weather, equipment malfunction, or contractor employee issues.