The following streets should see paving work during the week of May 28th to May 31st:
- Everett Street* (Paving on May 28, 2019)
- Barnesdale Road* (Paving on May 28, 2019)
- Robinhood Road* (Paving on May 28, 2019)
- Almont Street (milling and structure adjustment)
- Fairmount Street (milling and structure adjustment)
- Ashland Street (milling)
- Bloomingdale Drive (milling)
- Cambridge Road
- Massasoit Road (milling)
- Coburn Avenue (milling)
- Main Dunstable Road (Binder Paving and structure adjustment)
- Spit Brook Road (Milling, structure adjustment, and Binder Pave)
- West Hollis St (Milling and Binder Pave)
- Broad Street (Night work Milling and Paving)
Note: * These streets will be receiving shim and/or final top course next week. Please follow the direction provided by flaggers and contractors on site.
As always, this schedule is tentative and may change due to unforeseen circumstances such as weather, and equipment malfunction