The following streets should see work during the week of May 6th thru May 10th:
Hazel Avenue (structure adjustment)
• Pitarys Drive (structure adjustment)
• Westgate Crossing (structure adjustment)
• Spencer Drive (structure adjustment)
• Thoreau Drive (structure adjustment)
• Norwich Road* (final paving on May 6, 2019)
• Cannon Drive* (final paving on May 6, 2019)
• Robinhood Road* (final paving on May 7, 2019)
• Hazel Avenue* (final paving on May 7, 2019)
• Pitarys Drive * (final paving on May 8, 2019)
• Westgate Crossing* (final paving on May 9 and May 10, 2019)
• Main Dunstable Road (drop and plate structures)
Note: * These streets will be receiving shim and/or final top course next week. Please follow the direction provided by flaggers and contractors on site.
As always, this schedule is tentative and may change due to unforeseen circumstances such as weather, and equipment malfunction.